US company lands on the moon: Here’s how a KC firm helped boost its flames of innovation

February 23, 2024  |  Nikki Overfelt Chifalu

Burns & McDonnell's team at Intuitive Machines headquarters in the Houston Spaceport; photo courtesy of Burns & McDonnell

For the first time ever, a commercial spacecraft has touched down on the moon and Kansas City-based Burns & McDonnell provided innovation that helped to make it possible for Intuitive Machines and its Odysseus IM-1 lander, shared Brittney Swartz.

Intuitive Machines Nova C Lander

The local engineering, construction and architecture firm served as the designer and builder of Intuitive Machines’ new $40 million headquarters and flame range test facility, which opened in September 2023 in the Houston Spaceport. 

Although Burns & McDonnell was not involved with the moon mission itself, the firm’s team members still feel a sense of pride about how they helped empower the space exploration company, noted Swartz, design manager for the project and Burns & McDonnell aerospace and industrial operations manager.

“Getting to work with all those people and knowing that they put their heart and soul into that lander and to see it launch the week before and then land (Thursday), you know their hearts were huge,” she continued. “Your own heart just swells up for that, as well. It was awesome.”

Josh Foerschler, Burns & McDonnell

“It was a fun project,” added Josh Foerschler, the Burns & McDonnell aerospace, defense, and space business development leader.

Burns & McDonnell team members held a watch party — complete with Moon Pies for snacks — Thursday evening at their Kansas City offices as the Intuitive Machines lander reached its destination; the first American spacecraft to reach the surface of the moon since the Apollo program in 1972. 

“We were here quite late last night, just wanting to see those first images,” Swartz said. “It was great.”

Her team started working with Intuitive Machines on the building project in 2021, she said. At the time, the space company had its office and headquarters in a separate location than its manufacturing facility.

“Their key engineers had desks in two places, going back and forth,” Swartz explained. “And the opportunity came with Houston Spaceport to be able to build a facility there that actually was even right next door to their manufacturing space.”

Intuitive Machines headquarters in the Houston Spaceport; rendering courtesy of Burns & McDonnell

As the two companies started the ideation process, Swartz noted, they realized they needed to help Intuitive Machines solve another problem: a testing facility for its lunar landing engines that wouldn’t require loading them up onto a mobile vehicular test stand, driving them to an abandoned runway, and setting them up and taking them down in the Houston heat: a process that could take around 12 hours just for one test.

Intuitive Machines Flame Range Test Facility; image courtesy of Burns & McDonnell

So before even starting on the 105,572-square-foot headquarters, the engineering team worked with Intuitive Machines to design the flame range, consisting of a 3,800-square-foot reinforced concrete chamber surrounded by a 25-foot-high perimeter wall that encloses an additional 6,500-square-foot yard and delivers multiple advantages for Intuitive Machines testing protocols, according to Burns & McDonnell.

“This highly customized base for our aspirations goes far beyond office space,” said Jack Fischer, vice president of production and operations for Intuitive Machines at the ribbon cutting ceremony for the project in October 2023, according to a Burns & McDonnell news release. “It is an overarching complex with mission control, manufacturing and an advanced propulsion testing facility — the flame range — for the lunar lander engine. This was a facility and test area that didn’t exist before, and now, fueled by innovation, we can bring our vision to life.”

They broke ground on the flame range project in October 2021, Swartz shared, and it was up and running within nine months.

“That really launched their ability to go faster and deliver their contract with NASA even quicker,” she explained.

Brittney Swartz, Burns & McDonnell

Burns & McDonnell’s design-build delivery method allowed the engineering team to quickly respond and adapt to the challenges of a project of this scope, Swartz noted.

“That allowed us to be able to push the flame range building forward faster,” she continued. “Then we started back on the building and that allowed them to be testing their engine, as well as us figuring out what’s that workflow process for them in their manufacturing space. So the design-build method was really the only solution for them that would have allowed that amount of flexibility to respond to their changes.”

“Having this collaborative environment that we had with the design-build mentality with their team meant that we could respond quickly to their changes and react accordingly and not extend the construction even longer,” added Foerschler. “We were solving problems on the fly.”

 

startland-tip-jar

TIP JAR

Did you enjoy this post? Show your support by becoming a member or buying us a coffee.

Tagged , ,
Featured Business
    Featured Founder

      2024 Startups to Watch

        stats here

        Related Posts on Startland News

        Video: Witness a high-tech response to mock active shooter situation

        By Tommy Felts | March 31, 2016

        Kansas City Police on Thursday hosted a live demonstration of a high-tech, drone-enabled response to a mock active shooter situation in Kansas City.  The event, which was part of the inaugural Smart City Tech Summit, featured such public safety tools as gunshot detection tech, drones, social media monitoring, data analytics and more. Here’s a video recap of the…

        Events Preview: #OneDayKC

        By Tommy Felts | March 31, 2016

        There are a boatload of entrepreneurial events hosted in Kansas City on a weekly basis. Whether you’re an entrepreneur, investor, supporter or curious Kansas Citian, we’d recommend these upcoming events for you. WEEKLY EVENT PREVIEW #OneDayKC When: April 1 @ 8:00 am – 8:00 pm Where: Kauffman Foundation At #OneDayKC, college and high school students this day…

        Five years later: Google Fiber celebrates a Kansas City milestone

        By Tommy Felts | March 30, 2016

        Five years ago today, the Kansas City area heard the news that it would receive a transformative, residential gigabit Internet service. Hundreds of cities lobbied to be the first to receive Google Fiber, but ultimately, Kansas City, Kan. won the highly-sought-after service. And the world learned that on March 30, 2011. Five years later, Google…

        Mayor Sly James’ vision for Kansas City: Innovation and entrepreneurship

        By Tommy Felts | March 29, 2016

        In an address to constituents Tuesday, Kansas City Mayor Sly James broadly painted his vision for Kansas City and outlined what success for the area would look like. And at the cornerstones of his ideas for the next decade? The future of Kansas City hinges upon innovation and entrepreneurship. “With Google Fiber and the smart,…